Assignment Question(s):(Marks 5)
Question 1:
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4.
Job Work Center/Machine HoursDue Date (days) |
1 | A/3, B/2, C/2 | 3 |
2 | C/2, A/4 | 2 |
3 | B/6, A/1, C/3 | 4 |
4 | C/4, A/1, B/2 | 3 |
- Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5)
- What is the makespan? (Marks 0.5)
- How much machine idle time is there? (Marks 0.5)
- How much idle time (waiting time) is there for each job? (Marks 0.5)
- When is each job delivered? (Marks 0.5)
- Which department is the bottleneck? (Marks 0.5)
- Calculate the machine utilization? (Marks 0.5)
Question 2:
A public accounting firm requires the following activities
for an audit:
Activity | Immediate Predecessor | Activity time |
A | – | 3 |
B | A | 2 |
C | – | 5 |
D | B, C | 2 |
E | A | 4 |
F | B, C | 6 |
G | E, D | 5 |
- Draw a network for this project? (Marks 0.5)
- Make a forward pass and a backward pass to determine ES, LS, EF, and LF? (Marks 0.5)
- What are the critical path? (Marks 0.5)
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code “Newclient” for a 15% Discount!
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.

The post operation mangment 1 appeared first on The Nursing TermPaper.
"Is this question part of your assignment? We Can Help!"